Paul200
Established Member
Hi all
I've recently had to chisel my way under the wall of our house to install a mains water pipe (we had a private water supply previously). The foundations are actually a minimal 150mm approx. of concrete on top of the solid rock that is present very close to the surface here on the SW coast of Scotland - I hesitate to say 'Shale' in case I get fracked :?
Now the pipe is installed I'm wondering how to go about re-instatement. Should I replace the stone I removed from below the wall with concrete, or will back-filling with the spoil from the trench be sufficient? I haven't disturbed the existing 'foundation' because the pipe had to be as deep as I could get it - there is still some rock spanning the hole as well as the concrete.
My thoughts were to make a masonry culvert around the pipe and continue building up to the rock/foundation above. Then back-filling around this with the trench spoil. Any thoughts please?
Cheers
Paul
I've recently had to chisel my way under the wall of our house to install a mains water pipe (we had a private water supply previously). The foundations are actually a minimal 150mm approx. of concrete on top of the solid rock that is present very close to the surface here on the SW coast of Scotland - I hesitate to say 'Shale' in case I get fracked :?
Now the pipe is installed I'm wondering how to go about re-instatement. Should I replace the stone I removed from below the wall with concrete, or will back-filling with the spoil from the trench be sufficient? I haven't disturbed the existing 'foundation' because the pipe had to be as deep as I could get it - there is still some rock spanning the hole as well as the concrete.
My thoughts were to make a masonry culvert around the pipe and continue building up to the rock/foundation above. Then back-filling around this with the trench spoil. Any thoughts please?
Cheers
Paul